Open Access Research Article

Solving neutrosophic critical path problem using Python

, *

* Corresponding author · click or hover a name for details

pp. 897–911Vol. 45Issue 4May 2024DOI: 10.47974/JIOS-1614XML
Published Online:
08 Jun 2024
Article type:
Research Article
Language:
EN
Article no.:
JIOS-1614
Pages:
897–911

Abstract

The study observation offers a method for project control known as the Neutrosophic Critical Path Method (NCPM) which combines the traditional Critical Path Method (CPM) with neutrosophic sets. Dealing with actual global situations that frequently pose demanding situations for CPM specifically while initiatives involve interconnected operations. The presence of uncertainties creates hurdles during challenge execution, due to incomplete and uncertain data. By illustrating surroundings for instance this research outlines the transition from CPM to NCPM and highlights its advantages. Numerical examples have been implemented for solving NCPM, that discover solutions in the face of uncertainty. Furthermore, the advanced Python software specifically designed for network evaluation permits willpower of critical route lengths. This synthesis complements selection-making in project control that paves the manner for precise management of complicated situations.

Keywords

Subject Classifications

62A8690C0590C08

References

[1] C. C. Wei, P. H. Liu and Y. C. Tsai, “Resource-constrained project management using enhanced theory of constraint,” International Journal of Project Management, vol. 20, pp. 561–567 (2002). 
[2] H. Maylor, “Beyond the gantt chart: project management moving on,” European Management Journal, vol. 19, pp. 92–100 (2001).
[3] L. R. Foulds and J. M. Wilson, “Scheduling operations for the harvesting of renewable resources,” Journal of Food Engineering, vol. 70, pp. 281–292 (2005). 
[4] J. Kelley, E. James and M. R. Walker, “Critical-path planning and scheduling,” in Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (1959). 
[5] N. Paul Loomba, Management – a quantitative perspective, C. Macmillan, Ed., (1980). 
[6] S. M. Fahimifard and A. A. Kehkha, “Application of project scheduling in agriculture (case study: grape garden stabilization).,” American-eurasian Journal Of Agricultural And Environmental Science, vol. 5, pp. 313–321 (2009). 
[7] P. J. Bruce and M. J. Liberatore, “Project management software usage patterns and suggested research directions for future developments,” Project Management Journal, vol. 29, pp. 19–28 (1998). 
[8] L. A. Zadeh, “Fuzzy sets,” Information and control, vol. 8, pp. 338–353 (1965). 
[9] C. C. Chu, P. E. Zheng and D. D. Wang, “Analysis and modeling of fuzzy network planning considering complicated activity relationships,” J. Tianjin Univ, vol. 39, pp. 631–636 (2006). 
[10] K. T. Atanassov and S. Stoeva, “Intuitionistic fuzzy sets,” Fuzzy Sets and Systems, vol. 20, pp. 87–96 (1986).
[11] F. Smarandache, “A unifying field in logics: neutrosophic logic.,” in Philosophy, American Research Press, pp. 1–141 (1999).
[12] H. Wang, F. Smarandache, Y. Zhang and R. Sunderraman, “Single valued neutrosophic sets,” Infinite Study, vol. 12 (2010). 
[13] W. Abdelfattah, “A parametric approach to solve neutrosophic linear programming models,” Journal of Information and Optimization Sciences, vol. 42, no. 3, pp. 631-654 (2021).
[14] Jain, S., Kumar, S., Sharma, V. K., & Poonia, R. C. Peregrine preying pattern based differential evolution for robot path planning. Journal of Interdisciplinary Mathematics, 23(2), 555–562 (2020).
[15] S. Stefanov, “On the numerical solution of separable stochastic inventory control problems,” Journal of Information and Optimization Sciences, vol. 42, no. 3, pp. 533-561 (2021). 
[16] A. Ebrahimnejad and J. L. Verdegay, “A new approach for solving fully intuitionistic fuzzy transportation problems,” Fuzzy Optimization and Decision Making, vol. 17, pp. 447–474 (2018). 
[17] S. K. Das, T. Mandal and S. A. Edalatpanah, “A mathematical model for solving fully fuzzy linear programming problem with trapezoidal fuzzy numbers,” Applied Intelligence, vol. 46, pp. 509–519 (2017). 
[18] A. B. Mohamed, C. Victor and G. Abduallah, “Evaluation of the green supply chain management practices: a novel neutrosophic approach,” Computers in Industry, vol. 108, pp. 210–220 (2019). 
[19] A. Singh, A. Das, U. K. Bera and G. M. Lee, “Prediction of transportation costs using trapezoidal neutrosophic fuzzy analytic hierarchy process and artificial neural networks,” Ieee Access, vol. 9, pp. 103497–103512 (2021). 
[20] A. Thamaraiselvi and R. Santhi, “A new approach for optimization of real life transportation problem in neutrosophic environment,” Mathematical Problems in Engineering, vol. 2016, pp. 1–9 (2016). 
[21] I. Deli, “A novel defuzzification method of sv-trapezoidal neutrosophic numbers and multi-attribute decision making: a comparative analysis,” Soft Computing, vol. 23, pp. 12529–12545 (2019). 
[22] S. Zareei, “Project scheduling for constructing biogas plant using critical path method,” Renewable and Sustainable Energy Reviews, vol. 81, pp. 756–759 (2018).

Views: 325Downloads: 124Citations: 0